MMPA Architecture Engineering Interior Design Project Portfolio

Industrial - Degussa Facilities Master Plan

 






1  2  3  4  5
6  7  8  9  10
industrial

DEGUSSA (FORMERLY STOCKHAUSEN, INC.)

FACILITIES MASTER PLAN
GREENSBORO NORTH CAROLINA

 

A five-year Facilities Master Plan, developed for Stockhausen's Greensboro Campus included recommendations for site improvements, land acquisition, building adaptation, building renovation and new construction programs. Among other items, the four-phased work
included:

 

  - Existing facilities and site conditions study.
  - Identify issues to be addressed.
  - Develop alternative master plan concepts.
  - Select and develop appropriate concept.
  - Provide opinion of probable project cost.
  - Develop capital expenditure plan/schedule

 

MMPA also performed 26,000 sf of office renovation and laboratory renovation and expansion design for Stockhausen's Terrell and Doyle Street locations.